Berrenda 1
Berrenda 1

Berrenda Mesa Water District, Domestic Water Pipeline Replacement

Underground Utilities

Contract Amount: $1,383,969

Project Completion: August, 2012

Berrenda 2
Berrenda 3

Berrenda Mesa Water District, Domestic Water Pipeline Replacement

Blackwell’s Corner, California

W. M. Lyles Co. (WML) was the Design-Builder of this project which replaced the remaining portions of the existing 50 year old domestic steel water pipeline that had become a major maintenance problem for the District. Four new pipeline segments that contained a total of 63,700 LF of 4″ and 6″ PVC pipe were installed, along with bored crossing of Highway 33, two pressure reducing stations, and a metering facility. Additionally, the existing domestic water pump station was replaced with new pumps, piping, electrical and controls.

Owner:

Berrenda Mesa Water District

14823 Highway 33

Lost Hills, CA 93249

Owner Contact:

Phil Nixon

Design Engineer:

Provost and Pritchard Consulting Group

1800 30th Street, Suite 280

Bakersfield, CA 93301

Engineer Contact:

Jeff Eklund

W.M. Lyles Co. PM

Scott Burk