Fresno 2
Fresno 2

City of Fresno, Southeast Surface Water Treatment Facility

Water Treatment

Contract Amount: $162,089,360

Project Completion: September 2018

Fresno 1 1

City of Fresno, Southeast Surface Water Treatment Facility

Fresno, California

The SESWTF is designed to treat 80 MGD of surface (river) water from the Kings River to provide potable water to City residents. This greenfield project includes the following processes; flow control struc-ture, pre-treatment basins (flocculation/sedimentation with plate settlers), ozone disinfection structure, and filters (GAC gravity filter). The facility also includes an 8MG treated water reservoir, chemical building, treated water and backwash pump station; washwater recovery and solids lagoons and associated pump stations, electrical substation, operations building, maintenance building, all site utilities (with pipelines up to 84”), landscaping and pavement throughout the site, perimeter block wall and offsite road utilities.

Owner:

City of Fresno

1910 East University Avenue,

Fresno, CA 93721

Owner Contact:

Glenn Knapp, P.E.

Design Engineer:

Carollo Engineers, Inc.

12592 W. Explorer Dr., Suite 200

Boise, ID 83713

Engineer Contact:

Chris Johnson, P.E.

W.M. Lyles Co. PM

Tony Mueller