Cal Water, Northwest Bakersfield WTP Increase Net Treatment Capacity Upgrade
Water Treatment
Contract Amount: $4,394,558
Project Completion: August 2016
Cal Water, Northwest Bakersfield WTP Increase Net Treatment Capacity Upgrade
Bakersfield, California
The Northwest Bakersfield Water Treatment Plant has been unable to achieve design capacity due to high turbidity water reaching the membrane filters which resulted in excessive backwashing and reduced plant output. W. M. Lyles Co. with Black & Veatch as a design sub consultant was selected to provide design-build services to increase plant capacity to 8 MGD (net) and 10.4 MGD (peak) by installing a pretreatment system ahead of the membrane filters. The project included the construction of a 0.42 MG gallon concrete Pretreatment Basin with four Flocculating Mixers, and two trains of Plate Settlers with Straight Line Residuals Sludge Collecting equipment. Mechanical piping sludge draw off from the basins to sewer occurs via a hydraulic head pressure siphon. A new onsite PACL chemical system was installed that included tank storage, chemical feed and flash mixing facilities. The existing earth retention basin was reconstructed and concrete lined to handle the treatment process backwash, system overflows and site storm water runoff. All work was constructed on a very congested site with limited available space for equipment laydown and construction operations.
Owner:
California Water Service Co.
1720 N. First Street,
San Jose, CA 95112
Owner Contact:
Carmelo Sorce
Design Engineer:
Black and Veatch
10995 Gold Center Dr. #100
Rancho Cordova, CA 95670
Engineer Contact:
Ashu Shirolkaras
W.M. Lyles Co. PM
Jeff Mathiowetz