Western Riverside County Regional Wastewater Authority, 14 MGD Plant Expansion Project
Wastewater Treatment
Contract Amount: $57,822,148
Project Completion: January 2018
Western Riverside County Regional Wastewater Authority, 14 MGD Plant Expansion Project
Eastvale, California
Construction of a 6.0 MGD expansion to an existing conventional WWTP that increases the treatment capacity up to 14.0 MGD. Construction activities include headwork’s expansion with new bar screens, washer compacter, and grit classifier, two primary clarifiers, equalization basin, bioreactor, bio filter, secondary clarifier, cloth disc tertiary filters, chlorine contact basin, recycle water pump station, masonry digester building, solar drying beds and odor control system, five electrical buildings and associated site electrical, instrumentation, piping, paving, and fencing. Upgrades to the existing plant include new centrifuges, fixed steel digester covers, odor control facilities, masonry thickener building and chemical building upgrades.
Owner:
Western Riverside County Regional Wastewater Authority
14205 Meridian Parkway
Riverside, CA 92518
Owner Contact:
Tony Pollack
Design Engineer:
Albert A. Webb Associates
3788 McCray Street
Riverside CA. 92506
Design Engineer:
Aqua Engineering
533 W. 2600 S., STE 275 Bountiful, UT 84010
Justin Logan
W.M. Lyles Co. PM
Juan Ahumada