Wasco Water District, Wasco Stored Water Recovery Unit

Wasco Water District, Wasco Stored Water Recovery Unit Underground Utilities Contract Amount: $81,500,000Project Completion: Phase 1B 2007 Total Program – Ongoing Wasco Stored Water Recovery Unit Wasco, California Design-Builder of the District’s $200M Stored Water Recovery Unit Program. This overall program, delivered in phases, provides an east-west connection between the California Aqueduct and the District’s…

Cawelo Water District, Conduits D&E and Pump Stations

Cawelo Water District, Conduits D&E and Pump Stations Underground Utilities Contract Amount: $18,525,095Project Completion: June 2007 Cawelo Water District, Conduits D&E and Pump Stations Bakersfield, California This major infrastructure project expanded the District’s water recharge and recovery program, and improved its ability to deliver water to agriculture customers. Pipeline facilities installed included 12 miles of…

Semitropic Water Storage District, Stored Water Recovery Unit Phase 2K-XYZ Intertie Project

Semitropic Water Storage District, Stored Water Recovery Unit Phase 2K-XYZ Intertie Project Underground Utilities Contract Amount: $8,520,184Project Completion: June 2019 Semitropic Water Storage District, Stored Water Recovery Unit Phase 2K-XYZ Intertie Project Wasco, California W. M. Lyles Co. was the prime contractor on this progressive design-build project that connected portions of the District’s X, Y,…

The Regents of the University of California, UC Merced

The Regents of the University of California, UC Merced Underground Utilities Contract Amount: $57,442,031Project Completion: August 2020 The Regents of the University of California, UC Merced Merced, California WML partnered with Webcor Builders to provide subcontracting services to support the delivery of the UC Merced 2020 Project which nearly doubles the size of the existing…

Pacific Ethanol Plant

Pacific Ethanol Plant Waste to Energy Contract Amount: $68,716,457Project Completion: 2006 Pacific Ethanol Plant Madera, California Extensive Design-Build Ethanol Production Plant with a 40 MGY capacity. First major plant for the state of California with complete design and construction responsibility. Complete plant construction including site utilities, structural concrete, tanks and equipment; infrastructure and complete fabrication…

CR&R Incorporated Riverside County Environmental Center

CR&R Incorporated Riverside County Environmental Center Waste to Energy Contract Amount: $34,734,495Project Completion: March 2018 CR&R Incorporated Riverside County Environmental Center Perris, California This full project build out is ultimately capable of processing 300,000 tons per year of organic waste-to-energy. The facility was constructed in four Phases and generates biogas from organic waste materials such…

Calgren Renewable Fuels / Pixley Ethanol Plant

Calgren Renewable Fuels / Pixley Ethanol Plant Waste to Energy Contract Amount: $49,400,000Project Completion: 2008Calgren Renewable Fuels / Pixley Ethanol Plant Pixley, California Cal/OSHA Golden Gate Partnership Recognition Award recipient Primary Subcontractor of a 55 MGD Ethanol Production facility. Scope of work included concrete foundations, process piping, painting, insulation, structural steel, equipment installation, underground fire…

Victor Valley Wasterwater Reclamation Authority Biomethane Project

Victor Valley Wasterwater Reclamation Authority Biomethane Project Waste to Energy Contract Amount: $21,333,900Project Completion: November 2021 Victor Valley Wasterwater Reclamation Authority Biomethane Project Victorville, California W. M. Lyles Co. (Lyles) has teamed with Anaergia, a global leader in both the agricultural and the waste sectors to deliver the Victor Valley Wastewater Reclamation Authority (VVWRA) Biomethane…

Anaergia – Rialto Bioenergy Facility

Anaergia – Rialto Bioenergy Facility Waste to Energy Contract Amount: $109,755,091Project Completion: June 2021 Anaergia – Rialto Bioenergy Facility Rialto, California W. M. Lyles Co. has teamed with Anaergia, a global leader in both the agricultural and the waste sectors to deliver this one of a kind, progressive design-build project. The Rialto Bioenergy Facility (“RBF”)…

City of Rialto, S1 Wastewater Treatment Plant Improvements Project

The Wastewater Treatment Plant (WWTP), constructed in 1955 and eventually expanded in later years, was in need of upgrades in order to continue providing reliable service to the community. There are five plants that make up the overall WWTP. Plant 1 is currently not in use and Plants 2, 3, 4 and 5 are in operation.
The Rialto S1 WWTP Improvements Projects is a Joint Venture Project between W.M. Lyles Co. (WML)/AECOM and consists on the following approach and strategy: To build the Plant 5 expansion, new disc filters and new CCT Disinfection “off-line” and after appropriate startup and testing bring the new facilities into service. Construction of Plant 5 facilities is the critical path and accordingly construction timing of other plant facilities will be adjusted so that all new facilities are ready for performance testing at the same time. Once new Plant 5 facilities are online, commissioned and successfully complete a 30-day performance test, we will next take the existing Plant 5 Aeration Basins off-line for effluent gate replacement and the anoxic zone baffle wall modifications. After first Aeration Basin work startup and testing is complete, the second existing Aeration Basin will be taken off-line and the needed improvements conducted. The project is currently on time and on budget.